ABOUT THIS PROJECT
With a team of 5 employees working over the course of 1 weekend, Rhino have completed the installation of a 600 square metre temporary ceiling dust barrier in Louth, UK. Lincolnshire based Gelder Group, who employ over 300 people in the UK, contacted Rhino to construct a temporary suspended ceiling dust barrier in order to completely contain the dust generated during the construction of a new spa complex at the Kenwick Park Hotel. Because the building which houses the spa and pool area had been mostly completed, there was a potential issue whereby continuing construction work would create dust that would eventually require extensive high level cleaning of wooden pannelling and other finished surfaces.
In most cases where large dust and debris containment sheeting is used to create temporary partitions in factories and retail environments, we fix the sheets to a scaffolding structure. For this project, scaffolding was not required for access purposes, and to set up a temporary scaffolding just for the purposes of supporting the dust control sheeting would have been time consuming and costly.
Instead, Rhino proposed a support structure based around tensioned strapping.
With anchor points pre-fixed into the walls by the main contractor, the shrink wrap installation team from Rhino, used access towers to install 20 tensioned straps which radiated from around the building to a central ring. Finally a ratchet strap was attached to the central ring from above and tensioned to create a cone effect.
With the tensioned strapping support structure in place, the Rhino team used a 12 metre wide, 200 micro thick, flame retardant shrink wrap sheet to create the temporary construction ceiling. Overlaps between sheets were heat welded to create a continuously sealed skin. Around the edge of the building, temporary corrugated plastic panels were fixed to the walls and a skirt was installed between the roof sheeting and the wall. In this way, any dust from the construction work below could be completely contained.
At some point in the future, (hopefully soon), when the Covid 19 screens are no longer required, it will be easy to to cut down the shrink wrap in sections using a Stanley knife and fold it for recycling before removing the batten and track. (All Rhino Shrink Wrap sheeting products are 100% recyclable.) If graphics or signage is required, it is easy to apply self adhesive vinyl signage and zipped access hatches can ensure emergency exit routes remain accessible.
Compared to other Covid 19 barriers, such as solid hoarding, a shrink wrap screen offers more flexibility with regard to installation. Our standard product is available in sheets up to 7m wide x 15m long, and where joins are required, the sheets are heat welded so there is no limit to the size and shape of area that can be covered. As standard, our sheet is supplied in a white colour, but we can supply & install transparent screening also. If you prefer, we can provide ‘materials only’ and guidance to help you install the screens using your in-house teams.